1. Mandatory site and substrate requirements before work starts

Site temperature must be held steady between 15°C and 28°C, with relative humidity at 40% to 65%. The work area must be free of rain and standing water, doors and windows must be closed, and flooring should not be exposed to prolonged direct sunlight, which causes thermal expansion and distortion. Cement substrate strength must reach C20 or above, and moisture content must be 3% or less for sheet and 2.5% or less for LVT tiles. Where moisture exceeds these limits, a moisture barrier is essential, otherwise the floor will lift and the adhesive will fail later.

Flatness tolerance must be within 2mm under a 2-metre straightedge, and the floor must be free of dusting, hollow spots, cracks, oil and release agent residue. Old ceramic tile and epoxy floors must be ground overall to a rough profile and primed to improve adhesion. Where level differences are excessive, self-levelling compound must be used, and laying flooring directly over unevenness to hide defects is not permitted.

2. Technical standards for self-levelling

After cleaning and grinding, apply the dedicated primer in two coats, the second only once the first is dry, so the self-levelling layer does not shell or separate. Mix the compound strictly to the specified water ratio, leave it to stand until air bubbles disperse, then pour at an even rate, spread with a toothed rake and roll with a spike roller to release air. Standard contract levelling is 2mm to 3mm, increased to 3mm to 5mm for healthcare and sports floors.

The self-levelling layer must cure for at least 24 hours at normal temperature, extended to more than 48 hours in cold, damp conditions. Once dry, grind lightly overall and remove all dust before the next stage: residual dust greatly reduces adhesive bond strength.

3. Requirements for pre-laying and acclimatisation

On arrival, flooring must be left in its original packaging on site for at least 24 hours to acclimatise to temperature and humidity and release internal stress, otherwise shrinkage gaps will appear after laying. Check design and shade during dry laying, use product from a single production batch in one space, and lay joints in the direction of the light to minimise visible seams.

Leave an expansion gap at walls: 5mm to 8mm for sheet and 3mm to 5mm for LVT tiles. In large continuous areas, insert expansion joints every 10 metres to accommodate movement from temperature and humidity changes and prevent the whole floor from lifting or cracking.

4. Adhesive application and laying practice

Use only Gerflor's own environmentally sound flooring adhesive, and never mix in ordinary low-grade adhesive. Use an A2 notched trowel for sheet and an A4 notched trowel for LVT tiles, applying a thin, even coat to the levelled floor with no pooling or missed areas. Control open time strictly and lay the flooring once the adhesive has reached a dry-to-touch state: laying too early traps air, while laying after it has fully dried causes immediate delamination.

Once laid, roll the flooring repeatedly with a 50kg heavy roller, working from the centre outwards to expel all air and ensure full contact with the substrate. Leave allowance at sheet joints for welding grooves, butt LVT joints tightly with no gaps, and wipe up surplus adhesive immediately, since dried adhesive attacks the surface and leaves marks that are hard to remove.

5. Grooving and heat welding requirements

Sheet in hospitals, care homes, laboratories, kitchens and other wet areas must be heat welded and sealed. Once the adhesive has fully cured, groove with a dedicated groover to a depth of two thirds of the board thickness and a consistent width of 3.5mm, then blow all dust out of the groove. Use welding rod in a matching colour, set the heat gun to 350°C to 400°C and move at an even pace so the rod fills the groove completely with no voids.

Once cool, trim the weld in two passes: a rough trim first, leaving 0.5mm, then a fine trim flush with the surface after it has fully cooled, without cutting into the wear layer. LVT tiles are joined dry without welding; align the joints and fill with a dedicated sealant to prevent dirty water seeping underneath and breaking the bond.

6. Edge finishing at walls, door openings and equipment bases

Fit dedicated homogeneous skirting at wall expansion joints and seal the bottom with adhesive to stop moisture from the wall reaching the underside of the floor. Use transition strips at door openings and add a flat cover strip where levels change, to prevent the floor edge lifting and people tripping. Around ward washbasins, equipment bases and the plinths of operating theatre cabinets, turn the flooring up 50mm, with coved corners heat welded in one piece so there are no hygiene traps and daily sanitising is straightforward.

At columns and the bases of fitness equipment on sports floors, leave a separate expansion gap and fit a rubber edging strip to absorb movement, so long-term pressure from equipment does not crack or damage the flooring.

7. Post-installation care and protection

When laying is complete, keep the area closed for 24 hours at normal temperature before allowing foot traffic, and wait 48 hours before placing heavy furniture, hospital beds or trolleys. For seven days do not wash the floor with large volumes of water; dry mopping for dust is sufficient. During the curing period no welding or cutting may take place in the area, to avoid scorching the surface, and no sharp or hard objects may be dragged across the wear layer.

Sports flooring should be left for 72 hours before use, so the adhesive has fully cured and the shock-absorbing layer is stable. Healthcare and care facilities can carry out full sanitising once curing is complete, and hand over only after acceptance.

Most failures in Gerflor resilient flooring, including debonding, lifting, cracking and water ingress, stem from inadequate substrate preparation and non-standard installation. This specification covers substrate, levelling, laying, welding, edge finishing and curing, and only strict adherence in contract work will bring out the antibacterial, wear-resistant, waterproof and long-life performance of the floor. Guangzhou Junda Angu can provide standardised installation guidance to help contract projects deliver to specification.